รับเหมาติดต้้งไฟฟ้าโรงงาน

Scope of work

           : Modifying MDB cabinet for addition new breaker 400A
           : Making and Installing new DB panel 400A
           : Laying new cable Tray (Galvanized)200x200x100 with cover 
           : Pulling new power cable 2x(1 x 95 Sqmm),50%N,25%E

Due date : (25/9-14/11/2016)
Location : Bangkla pattana (CP group)  Chachoengsao Province.
Client     : Sahachon engineering.
Working team : Phopprom & MTC engineering.



Pipe rack cross over head for pulling new cable to new room.


Stream Boiler Room



Power cable CV 1 x 95 Sqmm.







Galvanized cable tray

MDB Room




Adding new breaker 400A
After modify MDB cabinet

Electrical room



Install cable tray


 Pulling new Power Cabl
New DB panel






Cable tray line


Install Temperature monitoring and timer control hot water tank.
Scope of work

           : Install control boxes (Temperature indicator and Timer controller)
           : Temperature monitoring and sounding and lighting when timer on
          
Due date : 14/11/2016
Location : Bankla pattana (CP group)  Chachoengsao Province.
Working team : Phopprom 
Hot water tank room

Wiring preparation work



Instaling control boxes



Control hot water three tank.



วันศุกร์ที่ 11 พฤศจิกายน พ.ศ. 2559

ปรับแต่งอุณหภูมิเตาอบ Tempering furnace temperature adjusting

Job requirement : Tempering furnace  temperature adjusting to closing Ramp trend graph
Trouble : Old temperature graph trend swing High and Low out of ranging  + 2 Degree and when changing data set point not climbing direct line ( Trend graph was curved line )

Client : Naripha kran chang
Working location : Armacell thailand ratchaburi


Temperature trend graph before PLC programing and PID adjust 


Prepare and checking PID parameter and Burner auto adjusting.




Temperature display monitoring  while checking PLC program over high rang 3.6 degree (while set point 120 degree)

After PLC Modified programing and  recheck temperature trend graph with DATAPAQ

DATAPAQ (temperature recorder)
Temperature trend graph comparing before and after result

Temperature trend graph before PLC programing PID adjust
Temperature trend graph  after PLC modified program 

วันพฤหัสบดีที่ 20 ตุลาคม พ.ศ. 2559

งานเพิ่มเติ่มแก้ไขปรับปรุงเครื่องจักร PLC HMI interface to robotic


Addition new Jigs parts no. (move from old line to new line )  auto welding by FANUC robotic Interface HMI (GOT 1000 series)
Used PLC Mitsubishi (Q06 series) communication with CC link system and interlock to portables Spot machines

Location : HPS Sriracha











And another line used YASKAWA robotic auto welding
CC link communicated 4 robotic interface by GOT 1000 series and PLC Q06 interlock to manual Spot portables










Tempering furnace ( Trouble : temperature swing high and low +5 degree and trend graph not ramp when changing set point)

PLC modify program for temperature adjusts to auto tune system by PLC (Fx series) used HMI Proface 4301 series

Cient :  Naripa Karnchang
Location : Armacell thailand Ratchaburi





Material before temper after tempering process expanded to ID 2"



์นิวโมเดล spot welding robot

รับงาน ติดตั้งปรับปรุงเครื่องจักร ระบบไฟฟ้าโรงงาน Robots ,Machines ,Utility System   เพิ่ม นิวโมเดล Jig Spot Welding ระบบอินเตอร์เฟส โรบ...

Company reference

Company reference

Company co-operate

Company co-operate

ค้นหาบล็อกนี้